Wet Plant Addition

Location: Marble Falls, TX

Type: Material Handling

Yards of concrete: 468

Pounds of rebar: 90,516

Completion: 2025

Descripción

This aggregate production facility has been upgraded with the addition of a new wet plant.

Thanks to close collaboration between our in-house engineer and the client’s engineering team, we strategically positioned the new plant to ensure a seamless integration of structural steel and conveyors, minimizing disruption and maximizing efficiency.

Our crews were instrumental in executing structural foundations and reinforced concrete work to support heavy steel structures and processing equipment.

Más proyectos

Dairy Farm Biogas Production Facility, Hico

Location: Hico, TX

Type: Energy

Yards of concrete: 3,146

Pounds of rebar: 853,448

Completion: 2024

Cast-In-Place Box Culvert, Terrell

Location: Terrell, TX

Type: Cast-In-Place Box Culvert

Yards of concrete: 841

Pounds of rebar: 191,250

Completion: 2023

Ready Mix, Ft. Worth

Location: Fort Worth, TX

Industry: Cement

Yards of concrete: 851

Pounds of rebar: 103,843

Completion: 2025